Accredo Packaging, Inc.

Overview

  • 6,664 sq ft office includes a lab and space for product testing.
  • 104,268 sq ft of condition manufacturing area that has a sophisticated chilled water system.
  • The warehouses consists of a load bearing concrete tilt wall and a structural steel main frame.
  • Mechanical attached roof system over a 3.1" (R-19) poly-iso roof.
  • 4,000 amps of underground service that supply the entire facility.

Need/Problem

  • Conditioned manufacturing and distribution facility.
  • Specialty foundation must be able to bear the weight of heavy machinery.
  • All equipment runs off of chilled water.
  • The ink room was highly flammable and required to meet certain codes in order
    to operate.

KDW Solution

  • Two (2) 500–ton Trane air-cooled chillers for manufacturing production equipment.
  • Specialty foundations (50’W x 96’L x 30”D in size) for equipment were installed in the manufacturing area.
  • 3,000 sq ft Ink Room that included a 4-foot-high concrete wall and spill barriers at overhead door and main door around the room to contain the ink inside if there were a spill.  Blowout panels were installed in the exterior, and blowout relief panels were installed at the roof in case an explosion would occur.  A special foam sprinkler system was also installed in this area.

 

Facility Type

North American Office/Distribution/Manufacturing Facility

Location

12682 Cardinal Meadows Drive
Sugar Land, TX

Size

350,000 sq ft

Site

14.7 acre site

"This project is LEED Silver certified and required high-end facades for an upscale business park."

 

Fill out my online form.

Accredo Packaging, Inc.

Facility Type

North American Office/Distribution/Manufacturing Facility

Location

12682 Cardinal Meadows Drive
Sugar Land, TX

Size

350,000 sq ft

Site

14.7 acre site

"This project is LEED Silver certified and required high-end facades for an upscale business park."

Overview

  • 6,664 sq ft office includes a lab and space for product testing.
  • 104,268 sq ft of condition manufacturing area that has a sophisticated chilled water system.
  • The warehouses consists of a load bearing concrete tilt wall and a structural steel main frame.
  • Mechanical attached roof system over a 3.1" (R-19) poly-iso roof.
  • 4,000 amps of underground service that supply the entire facility.

Need/Problem

  • Conditioned manufacturing and distribution facility.
  • Specialty foundation must be able to bear the weight of heavy machinery.
  • All equipment runs off of chilled water.
  • The ink room was highly flammable and required to meet certain codes in order to operate.

KDW Solution

  • Two (2) 500–ton Trane air-cooled chillers for manufacturing production equipment.
  • Specialty foundations (50’W x 96’L x 30”D in size) for equipment were installed in the manufacturing area.
  • 3,000 sq ft Ink Room that included a 4-foot-high concrete wall and spill barriers at overhead door and main door around the room to contain the ink inside if there were a spill.  Blowout panels were installed in the exterior, and blowout relief panels were installed at the roof in case an explosion would occur.  A special foam sprinkler system was also installed in this area.