Project Notes

  • Location
    Baytown, TX

  • Site
    156.38 acres

Jindal Saw Overview

  • KDW is installing natural gas and water lines in the Heat Treat building.
  • Installation of 4 (EA) Exterior Concrete Foundations at Heat Treat Building
  • Interior & Exterior Build Out of a multi-level Pulpit in Heat Treat Building
  • Turn-Key construction of 3 (EA) Operator Cabins in the ERW Building
  • Installation of 800' (LF) of 24" HDPE Storm Line & 1 (EA) Area Inlet
  • Repair and replace damaged Roof Sheets at the ERW Building
  • ERW Building Domestic Water Tie-Ins
  • Replace Well Water System with new Process Waterline and RPZ Backflow Preventer
  • Construct a new Pipe Exit Canopy at Heat Treat Building
  • 21,852 LF of Domestic/Fire Water and Sanitary Sewer (7' to 22' deep)
  • (3 ea) Roadbores totaling 283 LF
  • (23 ea) Fire Hydrants
  • (33 ea) Manholes

Throughout the different phases of construction, one thing impressed us the most was your focus in honoring your commitments. Secondly, The art of making a very complex project simple is a concept you have gracefully mastered.  We not only made the right choice with KDW we found a new partner.

Evan Barnett

General Manager

Typhoon Texas

We could not have picked a better partner, to help us in establishing a productive plant in SW Houston. KDW met with us several times, to develop an understanding of our needs. Once understood, they incorporated our proven program with their local knowledge of Municipality, available Materials, Sub Contractors, and other Project Management Guidance.

Kent Keebler

Project Manager

LKQ Corporation

The work and craftsmanship executed by the KDW team is truly inspiring and remarkable.They have a way of making what seems nearly impossible, possible and turning your dream into a reality. Their ability to adapt and meet strict deadlines will astonish you. They were an integral part to the true success of our construction phase and allowed us to become the Premier Water Park in Austin.

Ty Weitzel

General Manager

Typhoon Texas - Austin

KDW has been a true partner to our business since 2013. From small projects, complicated projects, to the largest projects in our business, KDW has been our single resource for success in the growth of our facilities. Their team brings vision, integrity, teamwork, and a true partnership to every aspect of our relationship. KDW is our single source for our development and contractor needs in all of Texas.

Bill Ader

Capital Projects Manager

Oldcastle Infrastructure, Inc.

In 2013 WIKA Process Solutions LP and GAYESCO INTERNATIONAL LCC started working with the KDW team to design & build our brand new manufacturing facility on a 13 acre lot in the Pasadena ship channel area. From start (concept & initial renderings) to finish (January 2015 moving in) the KDW team supported us in every step of the way.

Paul Lemmens

Wika

KDW has worked with us on two of our facilities, and we have been more than pleased both times. Their expertise in building for companies in the manufacturing industry resulted in facilities that were optimized for our purposes, resulting in smart layouts and highly-efficient spaces. When it comes to customer service, KDW has been affordable, personable, and timely. We highly recommend KDW for your company’s design/building projects.

BAUER Equipment America

Get In
Touch

Contact Us

KDW | Design. Build. Beyond.

Houston Office

5858 Westheimer, Suite 150, Houston, TX 77057

Phone: 713-541-5070 | Fax: 713-541-5072

East Texas Office

312 Old Tyler Road, Nacogdoches, TX 75961

Phone: 936-564-3329 | Fax: 936-569-7544